Scheduled Maintenance Notice – Equinix SY1 Data Centre (UPS B1 System Replacement)

Scheduled for Sep 8, 07:00 AEST  -  Sep 26, 17:00 AEST

Scheduled

Maintenance Window:
Date Range: Monday, 8 September 2025 to Friday, 26 September 2025
Daily Time (Local): 07:00 to 17:00 AEST
Daily Time (UTC): 21:00 to 07:00 UTC (previous day to current)

Location: Equinix SY1 (Sydney)

Summary:
Equinix will be undertaking a full replacement of the UPS B1 system at the SY1 data centre. This work is part of their ongoing UPS replacement program designed to ensure long-term reliability and minimise the risk of disruption to customer services.

Service Impact
Power Systems:
- All loads will remain on utility power throughout the activity.
- UPS-backed services will continue to operate on their primary UPS source.
- Redundancy will be reduced during the scheduled maintenance window.

Cooling Systems:
- Cooling redundancy will be maintained. No environmental impact is expected.

Additional Information:
Work will include the replacement of the UPS B1 system and associated batteries.

Maintenance activities are fully scripted and will be carried out by Equinix engineers with support from system vendors and service providers.

Only one UPS system will be worked on at a time to ensure operational stability.

No direct customer impact is expected, but reduced fault tolerance may exist during this period.

Customer Action:
No action is required. Services will remain operational and protected throughout the maintenance window. Equinix engineers will closely monitor all systems to ensure continued stability and service integrity.

For further details or questions, please contact our support team.
Posted Aug 04, 2025 - 09:38 AEST
This scheduled maintenance affects: Data Centres (Equinix SY1) and Regions (Sydney).