Summary:
Equinix will be performing scheduled quarterly maintenance on their Rotary UPS systems at the PE2 data centre. This proactive maintenance ensures the continued reliability and performance of power infrastructure supporting your services.

Service Impact
Power Systems:
- Loads will be transferred to generator power during the maintenance period.
- UPS-backed systems will be temporarily placed on an unprotected source.
- Power system redundancy will be reduced while work is underway.

Cooling Systems:
- Cooling system redundancy will be maintained. No environmental impact is expected.

Additional Information:
Each UPS unit will be serviced individually and placed in bypass mode one at a time to maintain overall system stability.

Generator power will fully support all customer loads during the maintenance. R-block capacity is available as a contingency.

No customer power interruptions are expected.

Customer Action:
No action is required from customers at this time. All work will be closely coordinated and monitored by Equinix and their approved vendors.

If you have any concerns or require further information, please contact our support team.
Posted Jun 30, 2025 - 15:00 AEST
This scheduled maintenance affects: Regions (Perth) and Data Centres (Equinix PE2).