Upcoming Power Maintenance in Equinix PE2
Scheduled Maintenance Report for Servers Australia
Completed
We have cancelled this maintenance as per recent correspondence from Equinix.
Posted Aug 02, 2021 - 09:05 AEST
Update
The maintenance listed has been rescheduled.

Please see the updated dates.
Posted Jul 23, 2021 - 16:09 AEST
Scheduled
During the times listed in this maintenance, power works will be carried out in the Equinix PE2 facility by Equinix technicians and onsite vendors.

Equinix will be installing an additional Static Transfer Switch (STS) in order to provide additional resilience to the A supply in Colo 1-1. In order for Equinix's vendor to perform these works safely, power to the Redundant (B) Source is required to be isolated.

Please be informed that single corded equipment may be impacted during the isolation of the B supply.

Impacted customers will be contacted separately with additional information.

If you have any questions related to this maintenance, please do not hesitate to reach out to our support team on 1300 788 862 or via a MySAU Portal case.
Posted Jul 23, 2021 - 15:31 AEST
This scheduled maintenance affected: Services (Dedicated Servers, Colocation), Regions (Perth), and Data Centres (Equinix PE2).