Hazardous Maintenance Works

Scheduled Maintenance Report for Servers Australia

Completed

The scheduled maintenance has been completed.
Posted Jun 22, 2021 - 17:00 AEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Jun 22, 2021 - 13:00 AEST

Scheduled

Engineers will be completing works to upgrade power capacity in two racks across Equinix SY3 and SY4 data centers.

Hosts in these racks will have their VMs evacuated and hosts will be put into maintenance mode temporarily.

No customer impact is expected.
Posted Jun 17, 2021 - 14:44 AEST
This scheduled maintenance affected: Data Centres (Equinix SY3, Equinix SY4) and Services (Private Cloud).