Equinix SY1 Edge Switch Replacement

Scheduled Maintenance Report for Servers Australia

Completed

The scheduled maintenance has been completed.
Posted Oct 05, 2022 - 05:00 AEDT

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 05, 2022 - 01:00 AEDT

Update

Because of unforeseen circumstances, we have rescheduled this maintenance to Wednesday the 5th of October between 1 AM & 5 AM.

We apologise for any inconvenience caused.
Posted Sep 27, 2022 - 11:26 AEST

Scheduled

During the times listed in this notice, network engineers will cut over colocation customers in Rack SY1:01:000010:0282 to a new edge top of rack switch.

We will contact customers individually that have equipment in this rack to provide further detailed information.

We expect no other services to be affected during this maintenance.
Posted Sep 20, 2022 - 17:08 AEST
This scheduled maintenance affected: Data Centres (Equinix SY1), Regions (Sydney), and Services (Network, Colocation).