Planned Works: Copper Cabling Decommission – SYD2 Data Centre

Scheduled Maintenance Report for Servers Australia

Completed

The scheduled maintenance has been completed.
Posted Sep 17, 2025 - 17:00 AEST

In progress

Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Sep 17, 2025 - 09:00 AEST

Scheduled

Date & Time:
Wednesday, 17 September – 9:00 AM to 5:00 PM (AEST)

Summary:
Our Network and Data Centre Operations teams will be decommissioning legacy copper cabling infrastructure in the Servers Australia SYD2 data centre.

Customer Impact:
No impact to customer services is expected. However, the nature of the work presents some risk to production fibre cabling within the facility.

Mitigation & Contingency:
Contingency plans have been prepared and will be enacted immediately if production cabling is disturbed, to minimise customer impact.
Posted Sep 16, 2025 - 13:18 AEST
This scheduled maintenance affected: Regions (Sydney) and Data Centres (SYD2).