Scheduled B2 UPS Core Expansion - SY4
Scheduled Maintenance Report for Servers Australia
Completed
The scheduled maintenance has been completed.
Posted Aug 20, 2020 - 07:00 AEST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Aug 18, 2020 - 07:00 AEST
Scheduled
Equinix's B2-UPS system has been identified as having a need to expand in capacity. Equinix has engaged manufacturers to install an additional UPS (Uninterruptible Power Supply) core designed for modular expansion, which is to be integrated into the existing infrastructure, without disruption to the operational environment.

During the scheduled window, Annual UPS maintenance, battery spot replacement, and UPS firmware updates will be undertaken to the UPS systems and associated batteries.

As the works will be undertaken to one system at a time, they will be performed without disruption to the operational environment and all critical power will continue to be supplied from an active UPS system or Generator. However, redundancy will be reduced.

Equinix engineers will work to ensure the maintenance does not impact your operations.
Posted Jul 30, 2020 - 11:06 AEST
This scheduled maintenance affected: Data Centres (Equinix SY4).