Scheduled Network Maintenance - Victoria
Scheduled Maintenance Report for Servers Australia
Completed
The scheduled maintenance has been completed.
Posted Oct 27, 2020 - 05:00 AEDT
Update
Stage 3/3 has been completed.
Posted Oct 27, 2020 - 03:52 AEDT
Update
Engineers are commencing stage 3/3 of this maintenance.
Posted Oct 27, 2020 - 03:39 AEDT
Update
Stage 2/3 has been completed.
Posted Oct 27, 2020 - 03:36 AEDT
Update
Engineers are commencing stage 2/3 of this maintenance.
Posted Oct 27, 2020 - 03:24 AEDT
Update
Stage 1/3 has been completed.
Posted Oct 27, 2020 - 01:44 AEDT
Update
Engineers are commencing stage 1/3 of this maintenance.
Posted Oct 27, 2020 - 01:29 AEDT
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Oct 27, 2020 - 01:01 AEDT
Scheduled
During the times listed in this notice, engineers will be performing network maintenance in Victoria. This maintenance will involve firmware upgrades for our core and distribution switching as well as moving new routing infrastructure into production to further increase capacity and redundancy for services in Victoria.

All services in Victoria are expected to be impacted during this window. Whilst this maintenance will be conducted in the Equinix ME1 facility, services in the 5GN MDC facility will also be impacted.

Service Impact Duration: 3x 5-minute interruptions

Please contact our Helpdesk via the MySAU portal if you have any queries or concerns.
Posted Oct 19, 2020 - 17:00 AEDT
This scheduled maintenance affected: Services (Network), Regions (Melbourne), and Data Centres (Equinix ME1).