rick.anzolin : #447

Hazard Notice - Power Upgrade SY4

Status:
Open
Type:
Scheduled
Start:
20/01/18 07:00
End:
20/01/18 13:00
Severity:
Low Impact
Description:
To meet the anticipated load growth at SY4 IBX, an additional 11KV Feeder will be installed in early 2018, in preparation for this, Equinix have engaged vendors to undertake an expansion of the 11KV Switchboards.

During this maintenance window a controlled shutdown of the incoming 11KV supply will be performed, and all site loads will be transferred to generator supply, this procedure has been planned to minimize the disruption to your operational environment and allow block redundancy to be maintained throughout.

Equinix engineers will work to ensure the maintenance does not impact your operations. This activity is fully scripted and may include the use of equipment system vendors and service providers.