rick.anzolin : #445

Hazard Notice - Vocus Perth UPS Testing

Status:
Closed
Type:
Scheduled
Start:
15/01/18 07:00
End:
18/01/18 07:00
Severity:
Low Impact
Description:
The following maintenance is not anticipated to have any effect on the normal operation of the facility. Please note that this is a hazard notification only and no action is required.

Start Date: Monday 15th January 2018 at 23:00 (UTC)
End Date: Wednesday 17th January 2018 at 05:00 (UTC)

This is part of the Vocus Data Centre Maintenance program to ensure all UPS are functioning as per design.

The UPS will continue to maintain the protected power load at all times during the scheduled window.

rick.anzolin
Tuesday, January 16th 2018 11:48am

Please note that due to weather conditions this UPS maintenance window has been cancelled, once works are re-scheduled we will update this status page.